Detroit Edison Energy Detroit Edison Energy - Fermi Nuclear Plant
Customer Since 1998
Challenge
Install temporary lighting system in an active torus in minimum time, requiring minimum number of installation technicians and minimum power supply lines.
Solution
50 magnetically mounted 4210 light fixtures plugged into 5 custom built 10 outlet power supply lines with special receptacles.
4210 Magnetic Mount Light Fixture
4210 Magnetic Mount Light Fixture
Custom Power Supply Line
Custom Power Supply Line
Results
  • Critical path project was completed on time with zero failures.
  • Bonus benefit: Due to unique polyurethane construction, all 4210 fixtures salvaged after outage, decontaminated of radioactive material and returned to service.